The report of MESPI for Hydropower plants is published

11 August 2021

foto

11.08.2021 -  The working group for "Review of administrative procedures implemented for hydropower plants and their impact on the environment", has finalized its work and presented the main findings through a report.

 

This working group was established by decision of the Minister of MESP, Liburn Aliu, in order to review the legality of procedural and administrative aspects of allowing these HPPs. The group included experts from MESPI and its subordinate agencies.

 

Some of the main findings of the report are as follows:

 

a) Despite the fact that the law regulates that a concession must be provided for the use of water for business purposes, the Ministry (MESPI) as the responsible authority for granting water rights, has not implemented the granting of the concession but has granted the water right with a water permit, which is a violation of the Law on Waters of Kosovo. The basic difference between a water permit and a concession, is in the fact that the concession is granted through a competitive process, while the water permit is not.

 

b) Not only the procedure defined by law for concession has not been implemented, but the issuance of water permits for water use for HPPs has been done in contradiction with the sub-legal act for water permit regarding the documentation, which must be attached to the application as well as the content of the water permit.

 

c) The issuance of water permits for HPPs was done without relying on a detailed and professional review and was not based on planning documents. Consequently, water permits have been issued and hydropower plants have been built in the areas where capital hydro-technical projects have been planned, thus endangering the realization of these facilities of strategic importance for Kosovo (as in the case of the Lepenci hydro system).

 

d) In the absence of a guide on how to draft and review the environmental impact assessment (EIA), which according to the law should be issued by the Ministry, the process of reviewing the EIA report and issuing the environmental consent has not had a well-defined performance, and an appropriate standard. EIA reports are generally poor. The most important aspects of the aquatic flora and fauna, such as the ecologically acceptable flow, the alluvium regime and the fish trails, are treated only superficially.

 

e) For all three HPPs of the Deçan cascade, construction permits and certificates of use have been issued by the Ministry, although all of these HPPs have a capacity of less than 10 MW, and consequently the issuance of a construction permit by law is the competence of the municipality. This was achieved by connecting the two HPPs ("Deçani" and "Belaja") with a single construction permit, since thus combined they have over 10 MW, and HPP "Lumbardhi" with the dam which is not built at all.

 

f) Practically, all HPPs are built in the immediate vicinity of rivers (watercourses) from which they generate energy, which is contrary to the provisions of the Law on Waters of Kosovo, which prohibits construction at a distance of less than 30 meters of solid lines (maximum 100-year water line).

 

For more download: The complete report